Maine Ground Snow Load: The Code and the Local Figures
Maine takes the national code's figure without a snow amendment of its own.
Maine takes the national code's figure without a snow amendment of its own
Maine adopts the national building code without a ground snow load amendment of its own, so the governing figure for a given address is the one the code's own table carries, and the body that applies it is The municipal code enforcement office, under the Maine Uniform Building and Energy Code. three figures published by Maine bodies themselves are set out below. 17 states are in the same position, which makes it the second commonest arrangement in the country.
The code's figure is applied to a given address by The municipal code enforcement office, under the Maine Uniform Building and Energy Code.
The following instructions are a guide to help code enforcement officials and designers determine ground snow loading across the State of Maine that meet MUBEC requirements. To determine ground snow loads for the MUBEC: 1) Use the following website and enter the exact address of the site to be designed: https://ascehazardtool.org/ 2) Select “ASCE/SEI 7-16” under Standard VersionMaine Snow Loads: Maine Uniform Building and Energy Code (MUBEC) | ASCE 7-16, read September 23, 2026. Read it at the source
The 3 figures published for Maine
three Maine figures, running from 70 lbs at Bangor to 80 lb/sqft at Hermon, every one of them quoted from the document it was printed in. Nationally 235 figures were read across 33 states.
The figure is keyed to the county in Maine, as it is in 21 states, so the county line rather than the town line is what changes the answer.
Each figure below appears in the unit and the wording its own document used, and links to the row it was printed in. A pound per square foot is a weight, and how deep a weight of snow sits depends on what that snow has been through since it fell, which is why the documents print the load and leave the depth to the engineer standing at the building.
80 lb/sqft
Hermon
a town next door to Bangor printing a higher figure than the city does
the document it was printed in, read September 23, 2026
80
Lewiston
printed in the city's filled in climatic and geographic design criteria sheet, where the column heading carries the units
the document it was printed in, read September 23, 2026
70 lbs
Bangor
the city's own building codes page prints its base climate data
the document it was printed in, read September 23, 2026
What Maine publishes
Maine does not publish a snow load document of its own, so the record below is the rule that puts the figure where it is rather than a table of figures.
The adopted code
Maine Snow Loads: Maine Uniform Building and Energy Code (MUBEC) | ASCE 7-16
Office of State Fire Marshal, Maine Department of Public Safety, November 2025
Open the document, read September 23, 2026
Case study terrain in Maine
Part of Maine is a case study area, meaning the published document expressly declines to give those places a figure and sends the designer back to the local building department for one. 16 states carry a rule like this, and it is the commonest reason a search for a single number comes back empty.
Large parts of Maine come back from the national tool as a case study area, and the State Fire Marshal's guidance prints the exact procedure a designer follows when that happens.
If “Case Study Required” is displayed, click the return button in the upper right corner and follow the below instructions. 1) Select “ASCE/SEI 7-22” under Standard Version 2) Select the appropriate Risk Category 3) Check “Snow” for Load Type 4) Click “View Results” 5) The Snow Load given should be reduced by the following equation to bring it to ASCE/SEI 7-16 loads: SL22 * 0.70 = SL16 (Value not less than100 lb/ft2)Maine Snow Loads: Maine Uniform Building and Energy Code (MUBEC) | ASCE 7-16, read September 23, 2026. Read it at the source
The office that holds the figure
The municipal code enforcement office, under the Maine Uniform Building and Energy Code: the state points every address at the national tool, and the town or city code office is who applies the answer.
Whoever publishes the number, the authority having jurisdiction over the parcel is the body that applies it, and it is the body a permit application goes to. Where a county has amended the state or national figure for its own terrain, the county’s figure is the one that governs there.
The municipal code enforcement office, under the Maine Uniform Building and Energy Code
the state points every address at the national tool, and the town or city code office is who applies the answer
This chapter provides express limitations on municipal home rule authority. The Maine Uniform Building and Energy Code must be enforced in a municipality that has more than 4,000 residents.
The rule that puts it there, read September 23, 2026

What Maine adopted
Technical Building Codes and Standards Board, Maine Office of Community Affairs adopts Maine Uniform Building and Energy Code (MUBEC) (MUBEC, with ASCE 7-16 for snow loads). Maine amended it rather than adopting it whole, and 22 states have done the same.
Editions matter more here than they look as though they should. Codes are adopted on a cycle of a few years, a county can amend one in between, and the national standard changed how it presents ground snow load between recent editions. 22 of the fifty states amended the code they adopted rather than taking it as written, and a state snow load table, where one exists, usually lives in that amendment.
The Technical Building Codes and Standards Board, established in Title 5, section 12004-G, subsection 5-A and located within the Maine Office of Community Affairs, is established to adopt, amend and maintain the Maine Uniform Building and Energy Code, to resolve conflicts between the Maine Uniform Building and Energy Code and the fire and life safety codes in Title 25, sections 2452 and 2465 and to provide for training for municipal building officials, local code enforcement officers and 3rd-party inspectors.Title 10, §9722: Technical Building Codes and Standards Board, Maine Revised Statutes, Maine Legislature, read September 23, 2026. Read it at the source
The same question in the other forty nine
14 states publish a ground snow load of their own, 17 adopt the national code without a snow amendment, and 19 leave every figure to a county or a city. 235 published figures were read across 33 states, and 16 states mark terrain their own document declines to give a figure for.
The table is ordered by how few steps stand between a reader and a figure keyed to their own town, which is a different ranking from how much snow a state gets.
| State | Who publishes the figure | Keyed to | Figures read |
|---|---|---|---|
| Vermont | The state drew a map | By region or zone | 14 |
| North Carolina | The state drew a map | By elevation | 3 |
| Wisconsin | The state drew a map | By region or zone | |
| Connecticut | The state publishes a table | County by county | 12 |
| Massachusetts | The state publishes a table | County by county | 12 |
| Michigan | The state publishes a table | County by county | 12 |
| Rhode Island | The state publishes a table | County by county | 12 |
| Utah | The state publishes a table | By elevation | 12 |
| Maryland | The state publishes a table | County by county | 10 |
| Indiana | The state publishes a table | County by county | 9 |
| Minnesota | The state publishes a table | County by county | 8 |
| New Jersey | The state publishes a table | County by county | 6 |
| Montana | A study the state adopted | By elevation | 12 |
| New Hampshire | A study the state adopted | By elevation | 12 |
| Texas | The adopted code | By region or zone | 6 |
| Alaska | The adopted code | By region or zone | 4 |
| New York | The adopted code | By elevation | 4 |
| Maine | The adopted code | County by county | 3 |
| Ohio | The adopted code | County by county | 3 |
| Arkansas | The adopted code | By region or zone | 2 |
| Louisiana | The adopted code | County by county | 1 |
| Alabama | The adopted code | One figure statewide | |
| Florida | The adopted code | One figure statewide | |
| Georgia | The adopted code | County by county | |
| Iowa | The adopted code | Not stated | |
| Kentucky | The adopted code | One figure statewide | |
| Nebraska | The adopted code | Not stated | |
| North Dakota | The adopted code | Not stated | |
| Oregon | The adopted code | By elevation | |
| South Carolina | The adopted code | County by county | |
| Tennessee | The adopted code | County by county | |
| California | Each building department | By elevation | 12 |
| Washington | Each building department | By elevation | 12 |
| Arizona | Each building department | By elevation | 11 |
| Nevada | Each building department | By elevation | 9 |
| Delaware | Each building department | County by county | 7 |
| Idaho | Each building department | By elevation | 6 |
| Oklahoma | Each building department | By region or zone | 6 |
| Virginia | Each building department | County by county | 4 |
| Wyoming | Each building department | By region or zone | 4 |
| Pennsylvania | Each building department | County by county | 3 |
| Colorado | Each building department | By elevation | 2 |
| Kansas | Each building department | County by county | 1 |
| South Dakota | Each building department | County by county | 1 |
| Hawaii | Each building department | Not stated | |
| Illinois | Each building department | Not stated | |
| Mississippi | Each building department | County by county | |
| Missouri | Each building department | Not stated | |
| New Mexico | Each building department | By elevation | |
| West Virginia | Each building department | County by county |
Maine ground snow load questions
Ground snow load in every state
Maine read September 23, 2026: Office of State Fire Marshal, Maine Department of Public Safety, Maine Snow Loads: Maine Uniform Building and Energy Code (MUBEC) | ASCE 7-16, and the county and city building departments that publish a figure where the state does not. Every value, adopting rule and case study rule above links to the document it was printed in. Codes are adopted on a cycle and a jurisdiction can amend one in between, so the document linked beside a line is what governs on the day. A ground snow load is an input to a structural calculation about one building by somebody who has been to it.